Scheduling parameters are not defined for production orders Message No. CT604
Diagnosis
No scheduling levels have been defined for production orders in Customizing for plant ADD1, order type PP01 and production scheduler * . You cannot conduct any scheduling until a selection ID for detailed planning, rough-cut planning or production rate planning has been entered. The selection ID determines the priority for the selection of the routing according to the criteria task list usage, type and status.
Moreover the scheduling type must be maintained.
Procedure
Maintain the scheduling parameters by entering a selection ID for detailled planning, rough-cut planning or production rate planning and select the scheduling type.
SOLUTION:
Go to T code OPU3 and maintain below for your plant

Regards, K S Adharsh