Cost center : change date

while cost center creation, i put wrong date for 'Valid from' and it get saved, how to change the date 'Valid from?'

i tried KS02 but not possible from there

89 Views
Unknown member
Nov 25, 2019

Hi, you need to create same cost center again for new analysis period.


Steps: Use KS01, enter same Cost Center and provide correct valid from date, enter all information and save.


Once you saved, it system will show you 2 validity periods for same cost center.