Activity type LAB-HR not set up for cost center FX01 CC-DRAWING Message No. CR061

Diagnosis

You are attempting to assign activity type LAB-HR to the work center. However, this activity type has not yet been set up in controlling area FX01 for cost center CC-DRAWING.

Procedure

  • Assign an activity type set up for cost center CC-DRAWING to the work center or

  • assign the desired activity type to cost center CC-DRAWING within cost center accounting.


SOLUTION: STEP 1: Go to T Code KP26 and maintain Planned Activity rates

Thanks, K S Adharsh