Cost element 500031 is not assigned to a cost component Message No. CK239

Diagnosis

The system attempted to generate the cost component split for the material, but discovered that no assignment has been made in cost component structure Y1 for cost element 500031 and possibly for origin group .

System Response

The cost component split is incomplete. The cost of goods manufactured in the cost component split is therefore less than in the itemization.

Procedure

Go into Customizing for Product Cost Controlling and carry out the assignment for cost component structure Y1 and chart of accounts ADD1. SOLUTION: STEP 1: Go to T Code OKTZ then select Cost Component Structure Y1 and click on Cost Components with Attributes

STEP 2: Then select Cost Component Structure and click on Assignment Cost Component - Cost Element Intervals

STEP 3: Click on New Entries and maintain as below for your Cost Component > Save.

Thanks, K S Adharsh

22 Views

Members

Get updates on new programs, workshops, the latest developments, and community activities, straight to your inbox.

Thanks for subscribing!

Programs
Instructor Led
Self-Paced Videos

Corporate Workshops

 

Gaurav Learning Solutions Reviews.png

© 2025 Gaurav Learning Solutions

bottom of page