Issue with releasing cost estimate and MMPV period

Hi All,


Hope someone could advise if a solution can be found for the following issue I encountered.

CK11N cost estimate was run on 1st Jan 21 which is day one of period 4 under fiscal year variant V9. However cost estimate can only be marked but not release as period 4 needs to be closed before cost estimate can be released. My understanding is that period 4 can only be closed if it is less than 10 days to period five. Has anybody had this issue before? Any idea how cost estimate can be released without closing period 5? Many thanks.


Regards,


KK


45 Views
Unknown member
Jan 03, 2021

Problem solved. It has to do with date setting on step 1 of CK40N

Members

Need Assistance? We're Here to Help!​

Connect with our team for quick support and expert guidance.

​

📞 Call / WhatsApp: +91 91583 97940
✉️ Email: info@gauravconsulting.com

Programs

Get updates on new programs, workshops, the latest developments, and community activities, straight to your inbox.

Thanks for subscribing!

Gaurav Learning Solutions Reviews.png

© 2026 Gaurav Learning Solutions. All Rights Reserved.

bottom of page